The A33 Basingstoke Road for 150 metres each side of Bottle Lane in Turgis Green will receive highway improvement works from 15th September 2015 for 8 nights, between the hours of 20.00 and 06.00.

The fist phase of these works are drainage and kerb repair to be carried out on Bottle Lane at its junction with the A33. This is to be carried out from 15th September for approximately 4 nights under temporary traffic lights therefore the road will not be closed.

The second phase of these works are carriageway resurfacing works on the A33 Basingstoke Road for 150 metres each side of Bottle Lane in Turgis Green. This is to be carried out from Monday 21st September for approximately 4 nights. Due to the large volume of daytime traffic on the A33, we require a night closure. Our contractor is aware of the issues concerning night working and will endeavour to keep noise to a minimum. Signed diversion routes will be set up and in place for the duration of the closure.